1) Haroonabad: work is completed, 2)Stenter: Electrical and mechanical work is continue and will be completed within a week. work is now just hold

1) Haroonabad: work is completed,
2)Stenter: Electrical and mechanical work is continue and will be completed within a week. work is now just hold due to unavailability of 50 pulse encorders which will be installed for auto width adjustment nadeem is importing the same from abroad this will take approx a week his concern persons are in factory and waitig for the encorders.
please Note that in future we must change the chain of machine because the chain which is installed on stenter have week strength and breaking at tension.
3) Sienging: with reference to your SMS information that nadeem will start the work of sienging in our factory but the work is still not started whereby the material is laying in workshop
4) Fiber shade: work has been completed
6) Jacket water system: Completed but on manual, we must install auto valve to upgrade the system ayaz will submit his quotation for same work.
For your information that ayaz is not responding for the Matter of WHR boiler . whereby i have frequently remind him for the same matter
7) Generator of haroonabad :Generator has been installed in Haroonabad and load observation report is Ok,
8) Backfilling work at haroonabad: Fazal paracha is doing the same work and the work will be completed within 4 to 5 days
9) Power house #1 roof flooring: completed
10) power house water tank work: Completed
11) water line: Connection of 2" water line is completed